GST Rate on Faecal Sludge Treatment Plant Works Contract as on 01.06.2022: Rajasthan AAR Rules 12% Applicable

Background and Context

The Rajasthan Authority for Advance Ruling (AAR) delivered its ruling in Advance Ruling No. RAJ/AAR/2026-27/13 dated 04.08.2026 in the matter of In re MTS-EIEL (JV) (GST AAR Rajasthan), addressing a significant question concerning the GST rate applicable to works contract services involving faecal sludge treatment plant (FSTP) infrastructure as on 01.06.2022.

The applicant, M/s MTS-EIEL (JV), operates as a GST-registered joint venture bearing GSTIN 08AAQAM9113R1ZN, with its registered office at 5/2, Shahid Amit Bhardwaj Marg, Malviya Nagar, Jaipur, Rajasthan — 302017. The ruling addresses a practical difficulty faced by contractors engaged in municipal water and sanitation infrastructure projects — specifically, the impact of a mid-contract GST rate revision on the financial viability of bids submitted under an earlier rate regime.


Nature of the Contract and Project Details

The joint venture was awarded a comprehensive works contract under Contract Package No. RSTDSP/FSTP-9 Towns/03 by the Rajasthan Urban Infrastructure Development Project (RUIDP) along with the respective Nagar Parishads and Nagar Palikas for various towns. The scope of work covered:

  • Design
  • Supply
  • Construction
  • Testing
  • Trial Run
  • Commissioning
  • Five years of Operation & Maintenance

of Faecal Sludge Treatment Plant (FSTP) infrastructure projects.

The accepted contract amount was Rs. 46,34,57,750/- (inclusive of a provisional sum of Rs. 2,11,00,000/-).

Key Chronology of Contract Events

Event Date
Tender Invitation 24.04.2022
Bid Submission 28.06.2022
Letter of Acceptance 30.09.2022
Notice to Proceed 28.11.2022

At the time the bid was prepared and submitted, the applicant factored in GST at 12% (6% CGST + 6% SGST) in the quoted contract price, relying on the rate prevailing under Notification No. 11/2017-Central Tax (Rate) dated 28.06.2017 as it stood on the relevant dates.


The GST Rate Change and Its Financial Impact

Following the issuance of Notification No. 03/2022-Central Tax (Rate) dated 13.07.2022, effective from 18.07.2022, the concessional rate entry that had governed the subject works contract was omitted. As a result, GST at 18% (9% CGST + 9% SGST) became applicable to works executed and billed on or after that date.

The applicant discharged GST liability at 18% on all subsequent invoices but contended that this created an additional tax burden of 6 percentage points over and above what had been considered in the original financial bid.


Questions Raised Before the Authority

The applicant sought an advance ruling on the following:

Q1) What is the applicable GST rate on Works Contract Services as on 01.06.2022?
(HSN Code 9954: S. No. 3/(iii)/(c) — pipeline, conduit or plant for (i) water supply (ii) water treatment, or (iii) sewerage treatment or disposal.)

Additionally, the applicant had raised a collateral issue regarding whether the additional 6% GST burden constituted a statutory tax liability recoverable from the contracting authority under the terms of the contract.


Jurisdictional Officer's Comments