CENVAT Credit on Capital Goods Survives Works Contract Classification: CESTAT Chennai's Ruling in Toshiba JSW Power Systems (P) Ltd. vs Commissioner of GST and Central Excise
Background and Context
The Customs, Excise and Service Tax Appellate Tribunal (CESTAT), Chennai, recently delivered a significant ruling in Toshiba JSW Power Systems (P) Ltd. Vs Commissioner of GST and Central Excise (CESTAT Chennai), addressing a longstanding dispute concerning the admissibility of CENVAT credit on duty-paid capital goods that were procured and installed through contractors within the assessee's own manufacturing facility.
The case involved two appeals arising from a common appellate order, both of which were heard and disposed of together. The central controversy revolved around whether the assessee — a joint venture manufacturer of super critical turbines, electric motors, electric generating sets and rotary converters — was entitled to CENVAT credit on excise duty paid on equipment and components supplied through contractors for installation inside its factory at Manali.
Factual Matrix
Toshiba JSW Power Systems (P) Ltd. engaged four contractors — M/s. Blue Star Ltd., M/s. ETA Engineering Pvt. Ltd., M/s. Metec Design & Construction Engineers India Pvt. Ltd., and M/s. Shakthi Electricals Chennai Pvt. Ltd. — to design, engineer, supply, erect, test and commission various systems within its manufacturing plant. These systems included HVAC units, stator coil shop infrastructure, HT/LT transformers, fire detection systems, industrial water systems, process cooling water systems, and street lighting and UPS.
Each engagement followed a standard documentation structure:
- A letter of intent was first issued to the contractor accepting a single consolidated price for the complete scope of work.
- This was followed by two separate purchase orders — one for supply of equipment, and another for installation, testing and commissioning.
- The manufacturers and dealers of the equipment issued duty-paid invoices naming the contractor as buyer but the appellant's factory as the consignee.
- The contractors billed separately for erection and commissioning, on which service tax was charged.
The assessee took CENVAT credit of:
- Excise duty reflected on manufacturers'/dealers' invoices — claimed as capital goods credit under
Rule 2(a)andRule 3(1)of the Cenvat Credit Rules, 2004 (CCR). - Service tax on the erection invoices.
The Department's Case and Demands
The Department, acting on intelligence, issued Show Cause Notice No. 24/2015 dated 25.09.2015, proposing recovery of ₹1,93,97,137/- representing credit availed during September 2010 to March 2015, under Rule 14 of the Cenvat Credit Rules, 2004 read with the proviso to Section 11A(1) of the Central Excise Act, 1944 (for the period up to 07.04.2011) and with Section 11A(4) thereafter. Interest and penalty under Rule 15(2) of the CCR read with Section 11AC of the Act were also proposed.
A subsequent Statement of Demand No. 18/2016 dated 02.05.2016 raised an identical demand for the period April 2015 to March 2016.
Three Grounds of the Department's Challenge
The Department's case rested on three distinct lines of argument:
First, that the contracts were composite EPCC (Engineering, Procurement, Construction and Commissioning) contracts, and the goods were the contractors' inputs, irreversibly absorbed into an immovable plant. Since the plant was not excisable as per Board's Order No. 58/1/2002-CX dated 15.01.2002 under
Section 37Bof the Act, the credit was impermissible.Second, that the contracts constituted works contract services taxable under
Section 65(105)(zzzza)of the Finance Act, 1994, and the value of goods was either exempted or excluded from service tax under Notification No. 12/2003-ST dated 20.06.2003 orRule 2Aof the Service Tax (Determination of Value) Rules, 2006. The Explanation appended toRule 3of the CCR consequently barred the assessee from availing this credit.Third, that the assessee had deliberately split composite contracts into separate supply and erection orders to facilitate the credit, warranting invocation of the extended period of limitation.
The Adjudicating Authority confirmed both demands, imposed equal penalties, and held that the Department had been kept in the dark about the dual-order structure. The Commissioner (Appeals) upheld these findings, adding that "the EPC Contractors have availed Notification No. 12/2003-ST" and that the extended period and penalties were justified.
Key Issues Before CESTAT Chennai
The Tribunal framed five core questions for determination:
- What was the true nature of the contracts — were separate supply and erection orders a genuine division or an artificial splitting of a works contract? And when did property in the goods pass to the assessee?
- Were the goods capital goods received and used in the factory, qualifying for credit under
Rules 2(a)and3(1)of the CCR? - Was credit barred by characterising the contractor's services as works contracts and invoking
Rule 2Aof the Valuation Rules read with the Explanation toRule 3of the CCR? - Was the extended period of limitation validly invoked for the first demand?
- Were interest and penalty sustainable?